Barr Mansion is USDA Certified Organic

Construction: Week Two and Three

Posted on: November 15th, 2010 by admin No Comments

Week two and three of construction have seen a ton of action!  Throughout week two we saw forms being constructed for the plinths that will hold the barn frame.  Rebar work began in the middle of the week for the new portion of the slab and also for the plinths.  The middle of the week also saw a section of a wall torn down!  Plumbing work began in the beginning of week three.  And finally, toward the end of week three, CONCRETE!  The forms for the plinths were filled with concrete so they can cure over the next few days.  We expect the barn frame to go up early in week four.  The pictures and videos that follow are in chronological order.

Check out the wall coming down here.  Video courtesy of Brandi Blaisdell.

Week Three of Construction

Check out a video of plinths being filled here.